Stellantis Detroit Assembly Complex-Mack

Project: Tank Farm and Waste Water Treatment Plant Retrofit
Project Location: Detroit, MI
Owner: Stellantis
Completion: 3/2022
Project Manager: Charles J West
As a prime contractor, oversee the install of a new Tank Farm for new assembly plant. Self-perform the mechanical piping and tanks portion of the project. Oversee electrical, civil, controls, insulation, and rigging.
As a prime contractor, oversee the install of a retro fitted Waste Water Treatment plant. Install of (2) new 450,000 gallon bolted batch tanks. Install of new welded Thickner tank. Install of multiple pumps and new fiberglass piping systems. Retrofit of flocculating tanks. Work with Stellantis and GLWA for final discharge permits.
Self-perform the mechanical piping and tanks portion of the project. Oversee electrical, civil, controls, insulation, and rigging.