Project Title : GM Orion RESS (Rechargeable Energy Storage System) Project Location: Lake Orion, MI Completion: 06/30/24 Project Manager: Dan Gregory Mechanical utility connections to the process equipment (mainly
Project Title : DTE Dry Fly Ash Conversion Project Location: Monroe , MI Completion: 12/31/2023 Project Manager: Charles West/ Dan Gregory Installation of a new fly ash conveyance system.
Project Location: DTE Monroe Power Plant Owner: DTE Completion: December 2023 Project Manager: Charles J West PMI to install over 30,000 feet of piping. The project consists of installing a
Project Title : Ford Engineering Lab (FEL) Project Location: Dearborn, MI Completion: 11/30/2023 Project Manager: Mike Roberts Design and Installation of the fire protection systems for the building renovation.
Project Title : Freeze Protection Pump Installation at Imlay City Pumping Station Project Location: Imlay City , MI Completion: 07/01/2023 Project Manager: Mario W. Anetrini Great Lakes Water Authority (GLWA)